Track Your Project
Stage-by-stage progress, photos and payments for your home — live.
Project AKB-24117 · Krishnan Residence
G+1 · 2,400 sq.ft · Standard package · HSR Layout, Bengaluru
Overall progress62%
₹49.2 LContract value
₹29.5 LPaid so far
142Days elapsed
Mar 27Handover
Construction stages
- Design approved12 Mar 2026
Plans and 3D elevation signed off.
- Foundation & plinth28 Apr 2026
Footings, plinth beam and backfilling complete.
- Ground floor slab30 Jun 2026
M25 RMC slab poured; cube test 27.4 N/mm².
- First floor slab22 Aug 2026
Slab and staircase complete; curing done.
- Brickwork & plasteringIn progress
AAC blockwork 80% done on first floor.
- Electrical & plumbingDec 2026
Concealed conduits and CPVC lines.
- Flooring & finishingJan – Feb 2027
Tiles, paint, doors and fixtures.
- HandoverMar 2027
Snag check, cleaning and keys.
Latest updates
- 14 site photos uploadedToday, 5:40 PM · Site engineer Vinay
- Block-work inspection passedYesterday · QA team
- Milestone 4 paid — ₹7,38,00024 Oct 2026 · Released after verification
- AAC blocks delivered (3,200 nos)20 Oct 2026 · LiteBlock
Your project team
- VSVinay ShettySite Engineer · daily visits
- KRKavya RaghavanProject Manager · weekly review
- RKRajesh KumarContractor · RK Constructions